Why would a four-lane toll road from Tampa Bay end at a traffic signal on Norvell Bryant Highway? If you drive CR 486 in Lecanto, you've probably wondered. That intersection is a placeholder, and how long it stays a placeholder decides a lot about the next few years along CR 486. That covers your commute and the construction you'll drive through. It also covers the county's rules for what can be built on the open land around the future ramps.
A Finish Line Built to Be Temporary
The extension from SR 44 to CR 486 opened to traffic on the afternoon of Monday, August 25, 2025. In its announcement, the Florida Department of Transportation called it a $103 million, three-mile segment that opened more than 500 days ahead of schedule. It also finished the SR 44 interchange.
The two ends of that segment were built very differently. At SR 44 you get a full interchange with a bridge carrying the parkway over the highway. At CR 486 the design is an at-grade intersection, which is the signal you stop at today.
The CR 486 end was never meant to be permanent. The next segment, Phase 3A, runs 5.5 miles from CR 486 north to CR 495. According to Florida's Turnpike, it will "complete the interchange at C.R. 486," add a partial interchange at CR 495, and widen and realign CR 495. The Turnpike's October 9, 2026 work-zone advisory puts the cost at about $195 million and says construction will continue through mid-2030. As of this month, the light at Norvell Bryant Highway has about three and a half years of work ahead of it.
Where the Toll Is Actually Charged
Because the parkway ends at an intersection, the toll on this stretch isn't collected at CR 486 at all. Before opening, a Turnpike spokesperson told the Citrus County Chronicle that the electronic gantries would sit on the SR 44 northbound on-ramp and the SR 44 southbound off-ramp.
The Turnpike's current West Central Florida toll rate schedule lists that SR 44 charge for a standard two-axle vehicle:
- SunPass: $0.28
- Toll-By-Plate: $0.58
That ramp toll is the charge for using the parkway between Lecanto's two big roads. If you're heading from the Target and Home Depot side of SR 44 up to CR 486, compare that toll with the free drive on CR 491. The Chronicle reports that the CR 491 widening phase linking the SR 44 and CR 486 corridor was finished and opened to traffic by the end of 2025.
The Construction Calendar From the Lecanto End
Phase 3A isn't the only work north of the light. Here are the parkway dates that matter for anyone who lives near CR 486:
| Milestone | Date | Source |
|---|---|---|
| SR 44 to CR 486 opens | August 25, 2025 | FDOT |
| Phase 3A, CR 486 to CR 495, begins | Mid-August 2025 | FDOT |
| Phase 3B, CR 495 to US 19, notice to proceed | May 4, 2026 | Superior Construction |
| Phase 3A, including the full CR 486 interchange, finishes | Mid-2030 | Florida's Turnpike |
| Phase 3B finishes | Late 2031 | Florida's Turnpike |
Florida's Turnpike describes the CR 495 to US 19 segment as about five miles long, with an estimated cost of $187 million. Its weekly advisories are where daytime lane closures get posted, including recent ones on N. Citrus Avenue/CR 495. If you drive north out of Lecanto regularly, the Turnpike's project page is worth bookmarking.
Some of the earlier work is already part of the local street grid. During Phase 2 construction, the realigned Knoll Road opened to traffic, and the new parkway overpass at Sanction Road was finished with its signals installed.
The County Is Drawing the Map Before the Ramps Exist
That four-year wait for the full interchange gives Citrus County a chance most places don't get. It can decide what belongs around a highway interchange before the interchange is finished. The tool is a comprehensive plan amendment called the CR 486 Interchange Management Area, or IMA, prepared with the consulting firm Wade Trim.
Here's the scale. Citizen Portal's summary of the May 7, 2026 Planning and Development Commission meeting describes an IMA of about 1,500 acres. It's divided into an Economic Development Target Area of roughly 772 acres and about 837 acres of mixed-use land. The commission voted unanimously to send it forward. On June 22, 2026, the Board of County Commissioners voted 4–1 to send the amendment to state agencies for review, according to Citizen Portal. Adoption is the stage that makes the plan final, and the county posts the amendment's adoption hearing and status on its development applications page.
At a planning workshop covered by the Chronicle, the draft included these provisions:
- Density: 6 to 12 residential units per acre in the mixed-use area, with bonuses up to 20 units per acre for public or community amenities
- Mixing required: nonresidential projects in the mixed-use area would need a residential component
- Excluded uses: mini-warehouses, RV and boat storage, stand-alone outdoor storage, and new car washes
- Design standards: landscaping, access management, pedestrian connections, a buffer along the parkway, and stormwater and utility requirements
These are draft terms, and the storage ban drew pushback in the room. Vice Chair David Bramblett told the commission, "People own stuff. It's needed." Truck traffic got its own debate. The Chronicle quoted commission member Jenette Collins:
"When the Suncoast finally makes it out to 19, I think that would be the ideal location for your truck stop. You've got 19, you've got the large movement of goods. County Road 486 isn't it."
Commissioner Stuart Bozeman agreed that those uses fit better farther north. For CR 486 drivers, the vision is a mixed-use corridor with homes, offices and shops at the interchange, while heavy freight uses wait for the parkway to reach US 19.
What Already Sits on That Stretch of Norvell Bryant
Two county filings show what kinds of projects are already lining up near the interchange.
YMCA Lecanto. At 4127 W. Norvell Bryant Highway, YMCA Lecanto has asked the county for permits to add four pickleball courts and build a 5,000-square-foot addition with interior renovations. For people who already use the Y, that's the nearest change on this list to their weekly routine.
A 79-acre mixed-use proposal. At 4134 W. Norvell Bryant Highway, SN Lecanto 486 LLC has proposed 300 multifamily units, 230,000 square feet of general commercial space and 130,000 square feet of professional and office space. According to the county's application tracker, staff asked the applicant for more information before public hearings can be scheduled. That mix of homes, retail and offices is the same pattern the IMA draft describes.
The corridor also has an outdoor asset that ties it together. The county's trailhead at CR 486 and Shimmer Terrace, by Meadowcrest, has parking, restrooms and a pavilion. When it opened, the county described it as a hub connecting the SR 44 bike lanes, the CR 491 multi-use path, access to the Withlacoochee State Trail, and the Suncoast Parkway path. The Turnpike's plans carry the Suncoast Trail along the parkway to CR 486 and continue it through Phase 3 as part of Florida's statewide trail system.
CR 491 also has another phase coming. The next segment covers 1.3 miles from Pine Ridge Boulevard to just north of Hampshire Boulevard and is still in planning and design. Put together, the parkway ramps, the CR 491 widening, the Y's expansion plans and the IMA proposal all point at the same few miles of central Lecanto, on a timeline that runs to mid-2030, when the CR 486 interchange is scheduled to replace the light.
If you own land or a home near CR 486 and want to know how the interchange plan might touch your corner of Lecanto, Trotter Realty follows these hearings and filings every week. Our team will walk you through what's on file near your address. Schedule a consultation.